Case Study
Below is an example of a Damper Replacement Project we recently completed.
To supply and install the following dampers:
• Replacement fresh air damper
• Recirculation air damper
• Exhaust air damper
• Each damper to be fitted with new actuators
• Due to coastal location all dampers must be painted with a protective paint finish
CASE STUDY
Below is an example of a Coil Replacement Project we recently completed.
To supply and install replacement heating coil suitable for a swimming pool and coastal environment.
• Coil connection positions to be identical to those on site to limit pipework modifications.
CASE STUDY
Below is an example of a Fan Replacement Project we recently completed.
To supply and install a direct replacement - Supply & Extract Fans and Motors.
• Works carried out on a weekend to ensure no disruption to the end users operation.
• Crane used to lift new equipment onto the roof.
• Redundant equipment removed.